From: Bimal Poudel
Sent: Monday, February 09, 2009 11:29 PM
To: anmfnepal
Cc: projects; binodshah; shankarrai
Subject: Re:request for Progress report updates

Dear Ngawang Ji and All,

Namaste!

I was out of internet access and as a result I could not respond to your email.

To give you a quick update of Samaj Sahakari Project:

  1. The company (Chesa International) has collected all equipments to supply to us as according to the quotation. They have been asking us for collecting the equipments from their store. But as you might know the East West Highway is blocked for already 8 days and for the reason we are not unable to receive the equipments from Chesa and send it to Bardibas.
  2. Right after the highway resumes, we will get all the products to Bardibas. Then we will send you the final report.

Should you have any queries, free feel to ask me.

Regards,

Bimal

 

2/11/09